Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

SSE, Equinor granted UK-first approval for Keadby carbon capture power station

© ShutterstockPost Thumbnail

The Keadby 3 carbon capture power station in the Humber has become the first power and CCS project in the UK to receive planning permission.

  • SSE Thermal and Equinor have received planning permission for a carbon capture and storage project in the UK.
  • The power station would capture up to 1.5 million tonnes of CO2 a year, representing around 5% of the country’s current 2030 CCS target.
  • The plant could be operational in 2027 assuming success in the authorities’ latest sequencing process leads to a final investment decision.

Developers SSE Thermal (LON:SSE) and Equinor (OSLO:EQNR) confirmed Thursday that the proposed plant in North Lincolnshire has now received a development consent order following permission from the Secretary of State for Business, Energy and Industrial Strategy (BEIS).

The pair said the order marked “a major step forward” for Keadby 3, which is currently in the due diligence stage of the UK Government’s Cluster Sequencing Process.

Under the plans, the power station would have a generating capacity of up to 910MW and capture up to 1.5 million tonnes of CO2 a year, representing around 5% of the UK Government’s current 2030 CCS target.

The plant would also be linked to the shared CO2 and hydrogen pipelines being developed as part of the Zero Carbon Humber and East Coast Cluster proposals.

Developers have said the plant could be operational “as early as 2027,” assuming success in the UK Government’s latest sequencing process leads to a final investment decision.

Site plans for Keadby 3 carbon capture power station.

In the meantime, a consortium of Aker Solutions, Doosan Babcock and Siemens Energy have already secured a major FEED contract for the project.

“This news is a significant milestone for our joint ambition to deliver clean, flexible and efficient power to support intermittent renewable generation and maintain security of supply,” said Equior SVP for low carbon solutions Grete Tveit.

“Together with SSE Thermal, we are delighted to be in a position to continue developing proposed Keadby 3 Carbon Capture Power Station. This project will not only support the decarbonisation efforts in the UK but will also have a positive impact on the local economy and supply chain, protecting existing jobs and creating new ones.”

SSE Thermal managing director Catherine Raw added: “To become the first power CCS project in the UK to receive planning consent is testament to the strength of Keadby 3, which is capable of playing a major role in achieving a net zero electricity system while providing vital flexible backup to renewables.

“This crucial project can underpin investment in shared CCS infrastructure and unlock wider decarbonisation and investment opportunities for the Humber, and we look forward to continued progress.”

Work at Keadby mirrors plans by SSE and Equinor at the latter’s Hydrogen to Humber project (H2H) at nearby Saltend, comprising a 600-MW auto thermal reformer (ATR) which will convert natural gas to hydrogen.

Captured CO2 from the process will be moved via a new 15-mile onshore pipeline and compressed at Centrica Storage’s Easington site, before being stored at the Endurance carbon store in the southern North Sea, around 90 miles off Teesside.

SSE Thermal and Equinor are also collaborating on plans for Peterhead Carbon Capture Power Station in the north-east of Scotland.